F. Schichau Danzig
Type | 227 Shipyard | |
Historical Name of Location | Danzig | |
Coordinates | 54.365806000, 18.644761000 |
Contributor: Al Griffis
ww2dbaseF. Schichau was a company that started in Elbing, Germany (now Elblag, Poland) in 1837, known initially for locomotives, and later as a shipwright. Having reached the maximum capacity at the small Elbing shipyard, in 1889, the company reached out to the government of Danzig, Germany (now Gdansk, Poland) for approval to build a shipyard on the Vistula River, and the negotiations dragged into the spring of 1890 on due to the conditions placed on the purchase of required land, but an agreement would eventually be reached in early 1890. Construction of the shipyard at Danzig began in Apr 1890. The land purchased was extremely wet, including bogs, and uneven with several small hills and valleys. To have a solid base to build on, tens of thousands of rocks of various sizes were laid as a foundation. Space between the rocks was filled in with thousands of pounds of sand. Originally there were two shipyard plans. One called for four slips large enough to construct warships and passenger liners equal to what the other major shipyards were producing. The other plan called for seven slips, and with the same requirement. Additionally, there must be enough room to add additional slips if needed, two slips must be over 200 meters in length and at least 30 meters in width. The first plan was not approved because it was argued the slips would be obsolete within 10 years. The second plan was approved. Six slips were approved with the ability to add additional ones if needed. The equipping pier would be 930 meters and the total area of the shipyard being 291,500 square meters. Other equipment approved being a floating dry dock, a floating crane with a 100-ton lifting capability and a hammer head crane with a 250-ton capability. Construction was completed in 1893. Ferdinand Schichau passed away in 1896, and his son-in-law, Carl Heinz Ziese, previously the manager of the F. Schichau repair yard at Pillau, Germany (now Baltijsk, Russia), took control of the company. In 1906, the floating crane was received. In 1914, the hammer head crane was installed. Ziese passed away in 1917, and Carl and Hildegard Carlson, Ziese's son-in-law and daughter, took over. After WW1, F. Schichau was nearly bankrupt, and it began receiving subsidies from the government to remain in operations building locomotives. In 1934, the F. Schichau yard in Danzig received modernization, including new tracks and cranes for slip IV.
ww2dbaseDuring WW2, at Danzig, F. Schichau built 62 Type VII C/41 submarines until 1944, and then switched to building Type XXI submarines, which 30 were built. Forced laborers from Poland, France, the Netherlands, Lithuania, Latvia, Germany, and Hungary were transported from satellite camps of Stutthof concentration camp to Danzig to be employed by F. Schichau. The prisoners received inadequate rations, which was limited to about half a liter of thin soup and 250 grams of bread per day, and they were given little to no winter clothing. Many forced laborers died from malnutrition, disease, and violence. The forced prisoners who perished were burned in a crematorium or buried in mass graves at the cemetery in Saspe (now the Zaspa district, Gdansk). In early 1945, a floating dock was transferred to Lübeck, Germany in advance of Soviet capture. Shortly after, a number of incomplete ships were transferred to Bremerhaven, Germany, along with the executive team headed by Hermann Noë. The company began to re-establish itself in Bremerhaven in the final months of the war.
ww2dbaseAfter the war, the city of Danzig was given to Poland, together with the control of the F. Schichau facilities. In 1950, The F. Schichau shipyard at Danzig was subsumed into the Lenin shipyard. Meanwhile, the F. Schichau name lived on with Noë's new operations in Bremerhaven. It remained in operations until 2009 when it was acquired by Schichau Seebeckwerft.
Last Major Update: Sep 2022
Ships Constructed at F. Schichau Danzig
Ship Name | Yard No | Slip/Drydock No | Ordered | Laid Down | Launched | Commissioned |
Kurmark | 25 Aug 1939 | |||||
T52 (Planned) | 1720 | 28 Mar 1944 | ||||
T53 (Planned) | 1721 | 28 Mar 1944 | ||||
T54 (Planned) | 1722 | 28 Mar 1944 | ||||
T55 (Planned) | 1723 | 28 Mar 1944 | ||||
T56 (Planned) | 1724 | 28 Mar 1944 | ||||
T57 (Planned) | 1725 | 28 Mar 1944 | ||||
T58 (Planned) | 1447 | 28 Mar 1944 | ||||
T59 (Planned) | 1448 | 28 Mar 1944 | ||||
T60 (Planned) | 1449 | 28 Mar 1944 | ||||
U-3504 | V | |||||
U-3505 | V | |||||
U-3510 | VI | |||||
U-3511 | VI | |||||
U-3512 | VI | |||||
U-3515 | V | |||||
U-3516 | V | |||||
U-3517 | IV | |||||
U-3518 | IV | |||||
U-3519 | IV | |||||
U-3520 | IV | |||||
U-3521 | II | |||||
U-3522 | II | |||||
U-3523 | III | |||||
U-3524 | III | |||||
U-3525 | VI | |||||
U-3526 | VI | |||||
U-3527 | VI | |||||
U-3528 | VI | |||||
U-3538 | 1683 | III | 6 May 1944 | |||
U-3539 | 1684 | II | 6 May 1944 | |||
U-3540 | 1685 | II | 6 May 1944 | |||
U-3541 | 1686 | VI | 6 May 1944 | |||
U-3542 | 1687 | III | 6 May 1944 | |||
U-442 | II | |||||
U-736 | III | |||||
U-737 | II | |||||
U-738 | II | |||||
U-745 | VI | |||||
U-746 | VI | |||||
Schlesien | 19 Nov 1904 | 28 May 1906 | 5 May 1908 | |||
Dithmarschen | 11 Feb 1935 | 6 Jun 1936 | 12 Jun 1937 | 20 Jul 1939 | ||
Nordmark | 14 Nov 1936 | 5 Oct 1937 | 16 Jan 1939 | |||
Ermland | 18 Feb 1937 | 17 Dec 1937 | 2 Sep 1940 | |||
Q (Planned) | IV | 8 Aug 1939 | 1 Mar 1941 * | 1 Mar 1943 * | 1 Apr 1944 * | |
SP4 (Planned) | IV | 1 Mar 1942 * | 1 Jun 1943 * | 1 Dec 1944 * | ||
SP5 (Planned) | V | 1 Mar 1942 * | 1 Jun 1943 * | 1 Dec 1944 * | ||
N (Planned) | 129 | V | 1 Oct 1941 | 1 Jan 1944 * | 1 Jul 1945 * | 1 Jul 1946 * |
Q (Planned) | IV | 1 Dec 1941 | 1 Jun 1944 * | 1 Nov 1945 * | 1 Dec 1946 * | |
U-3535 | 1680 | IV | 6 Nov 1943 | 26 Nov 1944 | ||
U-3536 | 1681 | IV | 6 Nov 1943 | 27 Nov 1944 | ||
U-3537 | 1682 | III | 6 Nov 1943 | 20 Dec 1944 | ||
SP18 (Planned) | IV | 1 Mar 1945 * | 1 Jun 1946 * | 1 Dec 1947 * | ||
M2 (Planned) | IV | 1 May 1943 | 1 Aug 1945 * | 1 Feb 1947 * | 1 Feb 1948 * | |
SP19 (Planned) | VI | 1 Sep 1945 * | 1 Dec 1946 * | 1 Jun 1948 * |
* Projected dates; not actual
Slip/Drydock Utilization
[Con]: Construction; [FO]: Fitting Out
F. Schichau Danzig Interactive Map
Photographs
Maps
F. Schichau Danzig Timeline
18 Apr 1890 | Construction for a new F. Schichau shipyard in Danzig, Germany (now Gdansk, Poland) began. |
6 Jun 1936 | The keel of Dithmarschen was laid down by F. Schichau in Danzig. |
12 Jun 1937 | Dithmarschen was launched by F. Schichau in Danzig. |
29 Jan 1945 | The construction of U-3538, U-3539, U-3540, U-3541, and U-3542 was suspended at the F. Schichau shipyard in Danzig. |
30 Mar 1945 | U-3538, U-3539, U-3540, U-3541, and U-3542, still under construction, were captured by the Soviets at the F. Schichau shipyard in Danzig. |
Did you enjoy this article or find this article helpful? If so, please consider supporting us on Patreon. Even $1 per month will go a long way! Thank you. Share this article with your friends: Stay updated with WW2DB: |
WW2-Era Place Name | Danzig |
Lat/Long | 54.3658, 18.6448 |
- » 1,150 biographies
- » 337 events
- » 43,622 timeline entries
- » 1,240 ships
- » 349 aircraft models
- » 207 vehicle models
- » 372 weapon models
- » 123 historical documents
- » 259 facilities
- » 470 book reviews
- » 28,499 photos
- » 432 maps
Winston Churchill, 1935
Please consider supporting us on Patreon. Even $1 a month will go a long way. Thank you!
Or, please support us by purchasing some WW2DB merchandise at TeeSpring, Thank you!